KOMPARASI OPTIMALISASI PERALATAN MEKANIS PADA KEGIATAN PENGUPASAN OVERBURDEN MENGGUNAKAN METODE KAPASITAS PRODUKSI DAN METODE OVERALL EQUIPMENT EFFECTIVENESS (OEE)

Hisni Rahmi, Afni Nelvi

Abstract


The company's production target in overburden stripping is 200 BCM/hour, while the actual in the field is still below the production target. Therefore, it is necessary to optimize production using queuing theory. Queuing theory is a method that can be used to calculate and model the behavior of trucks and loaders in open pits so that loading activities take place better. The purpose of this research is to optimize the productivity of digging and loading equipment using queuing theory. The primary data needed is the loading and unloading cycle time, transportation equipment cycle time, repair time, standby time, working time. Secondary data needed in the form of available working time by the company. The results of the study resulted in the actual productivity of the excavator is 140.59 BCM/hour with the production capacity method and 106.68 BCM/hour using the OEE method, while the dumptruck is 135.33 BCM / hour with the production capacity method and 161.78 BCM/hour using the OEE method where it has not met the production target. Productivity after being optimized for excavator loading and unloading equipment increased by 52.74% to 297.49 BCM / hour using the production capacity method and increased by 58.85% to 259.24 BCM / hour using the OEE method, while dumptruck productivity increased by 36.85% to 214.31 BCM / hour with the production capacity method and increased by 22.47% to 208.68 BCM / hour using the OEE method which has met the production target.

Keywords


optimization, mechanical tools, overburden stripping, queuing theory

References


Dewi, N. C., & Rinawati, D. I. (2015). Analisis Penerapan Total Productive Maintenance (TPM) dengan Perhitungan Overall Equipment Efectiveness (OEE) dan Six Big Losses Mesin Cavitec PT Essentra Surabaya (Studi Kasus PT Essentra). Industrial Engineering Online Journal, 4(4), 17.

Frediana, Y., & Ansosry. (2019). Optimalisasi Produksi Alat Gali Muat dan Alat Angkut pada Pengupasan Overburden dengan Menggunakan Metode Antrian dan Kapasitas Produksi di Pit 3 PT . Jambi Prima Coal , Kecamatan Mandiangin , Kabupaten. Jurnal Bina Tambang, 6(2), 157–172.

Hidayati, A. P. D., Permana, I. S., & Oktavia, M. (2021). Optimasi Alat Gali Muat Dan Alat Angkut Menggunakan Metode Teori Antrian Dan Kapasitas Produksi Pada Kegiatan Coal Getting Di Pt Natural Artha Resource. Mine Magazine (MineMagz), 2(1).

Mohammadi, M., Rai, P., & Gupta, S. (2017). Performance evaluation of bucket based excavating, loading and transport (BELT) equipment - An OEE approach. Archives of Mining Sciences, 62(1), 105–120. https://doi.org/10.1515/amsc-2017-0008

Nurwulan, N. R., & Fikri, D. K. (2020). Analisis Produktivitas dengan Metode OEE dan Six Big Losses : Studi Kasus di Tambang Batu Bara. IKRA-ITH EKONOMIKA, 3(3), 30–35.

Nuryono, A. (2018). Analisis Efektifitas Kinerja Excavator Pada Aktifitas Ob Removal Penambangan Batubara. Journal Industrial Manufacturing, 3(2), 79–88.

Pradana, S. Y., Oktafianto, K., & Nuruddin, A. W. (2020). Optimasi Dump Truck Dengan Metode Kapasitas Produksi Dan Teori Antrian Pada Tambang Batu Kapur Di PT . Bio Alam Indonesia Persada. Jurnal Matematika, 02(02), 52–58.

Putri, N. A., & Gusman, M. (2018). Optimalisasi Produksi Shovel Komatsu 3000E-6 dengan Metode Overall Equipment Effectiveness ( OEE ) Pada Pengupasan Lapisan Overburden di Pit 2 Tambang Banko Barat PT . Bukit Asam ( Persero ) Tbk. Jurnal Bina Tambang, 3(3), 1300–1309.

Rija, S., & Anaperta, Y. M. (2020). Optimalisasi Peralatan Tambang dengan Metoda Overall Equipment Effectiveness (OEE) untuk Memenuhi Target Produksi Pengupasan Overbuden Bulan Agustus 2019 di Pit 1 Utara Bangko Barat PT. Satria Bahana Sarana Tanjung Enim Sumatera Selatan. Bina Tambang, 5(3), 102–110.

Sefrizni, A., & Kasim, T. (2018). Analisis Kebutuhan Alat Gali Muat dan Alat Angkut Menggunakan Simulasi Teori Antrian Pada Produksi Overburden di PT Haswi Kencana Indah Kecamata Sumay, Kabupaten Tebo ProvinsiJambi. Jurnal Bina Tambang, 4(3), 260–270.

Sosantri, B. J., Yulhendra, D., & Prabowo, H. (2018). Optimalisasi Peralatan Tambang dengan Metoda Overall Equipment Effectiveness (OEE) di Pit 1 Penambangan Batubara Banko Barat PT Bukit Asam (Persero Terbuka) Tanjung Enim Sumatera Selatan. Jurnal Bina Tambang, 3 (2), 1–20.

Tobe, A. Y., Widhiyanuriyawan, D., & Yuliati, L. (2018). The Integration of Overall Equipment Effectiveness (Oee) Method and Lean Manufacturing Concept To Improve Production Performance (Case Study: Fertilizer Producer). Journal of Engineering And Management In Industrial System, 5(2), 102–108. https://doi.org/10.21776/ub.jemis.2017.005.02.7

Yazdi, P. G., Azizi, A., & Hashemipour, M. (2018). An Empirical Investigation of the Relationship between Overall Equipment Efficiency (OEE) and Manufacturing Sustainability in Industry 4.0 with Time Study Approach. Sustainability (Switzerland), 10(9). https://doi.org/10.3390/su10093031




DOI: http://dx.doi.org/10.36275/stsp.v22i2.529

Article Metrics

Abstract view : 216 times
PDF (Bahasa Indonesia) - 92 times

Refbacks

  • There are currently no refbacks.


Copyright (c) 2022 Hisni Rahmi, Afni Nelvi

Creative Commons License
This work is licensed under a Creative Commons Attribution 4.0 International License.

Penerbit : Sekolah Tinggi Teknologi Industri Padang


Alamat:
Jalan Hamka no.121 Tabing Padang. Indonesia
email: info@sttind.ac.id
HP:082386758367